Category: Nezaradené
Invite for exhibition 25.8 – 6.9.2016
On August 25th beginning at 17:30 there will be a little, informal exhibition of design students works from summer semester – complemetary elements for Duna bird watching – bike stands, info tables, additional sitting.
Exhibition will be up until September 6th, 2016.
First test bird watching during Day of opened doors II., June 12, 2016
The first testing bird watching with Ján Dobšovič from agency bird watching.sk and the Day of Opened Doors II. was held on June 12, 2016 within festival Midsummer on Danube / Slnovrat na Dunaji. Continue reading First test bird watching during Day of opened doors II., June 12, 2016
Surface finishing
The last phase is the cladding surface finishing. Because of the rainy wetter in past days, there were already grey stains, so we decided to sand the surface to get the homogeneous surface color at least at the beginning of the surface finishing. The plane zones were sanded with the abrasive band grinding machine and the curvy zones were done by disk vibration sander. Continue reading Surface finishing
Completing the outdoor and indoor cladding
Continue reading Completing the outdoor and indoor cladding
Workshop nr. 2: Day 10, Friday April 8 – Day of opened “doors” and pre-opening good-bye party
Last day of the final workshop , on April 8, 2016 we have organized Day of opened “doors” and pre-opening good-bye party.
Workshop nr. 2: Day 5 – 9, Sunday April 3 – Thursday April 7
In this phase there were designed and manufactured plywood ribbons supported by timber. They are creating supporting structure for back leaning by the main big beam. Continue reading Workshop nr. 2: Day 5 – 9, Sunday April 3 – Thursday April 7
Workshop nr. 2: Day 1 – 4, March 29 – April 1
After Easter, we continue with 2nd Spring workshop. It is our 4th meeting together. Continue reading Workshop nr. 2: Day 1 – 4, March 29 – April 1
Day 12 – 14, Monday March 21 – Wednesday March 23
The relay was took by Slovak students and teachers from FA STUBA, thus the basic structure has to be prepared for the next phase after Easter – putting a wooden cover carpet on the top surface. Continue reading Day 12 – 14, Monday March 21 – Wednesday March 23
Day 9 – 11, Friday March 18 – Sunday March 20
The most time consuming phase has started – cutting and fixing of crossbeams between the big glued plywood beams.
Continue reading Day 9 – 11, Friday March 18 – Sunday March 20